Construction of Metsä Group’s giant Rauma sawmill on schedule
Construction work on the site has advanced in line with the master schedule. The sawmill buildings were completed in November. The final HVAC work and installation of equipment and machinery are under way on the sawmill construction site in Rauma. The buildings for the sawline and the sorting lines of green and dried sawn timber have been completed. Line machinery and equipment are currently being installed. Equipment for green sorting will be installed on the green sorting line as well as the sticking and stacking line. Construction of the sawmill infeed and ...